Campus Updates
11.5.24 - 2nd-4th grade have returned to their homerooms in the Lawson Building as of today.
CrossOver has estimated that work will be completed in the Lawson Building on Tuesday, October 29. We, therefore, anticipate having students and staff occupying the Lawson Building for classes beginning on Tuesday, November 5. Please keep in mind that construction timelines can change, but there is hope on the horizon. Should anything change, Aristoi Classical will provide updates to the community as CrossOver updates Aristoi.
Art and Music Portable
- 11.15.24 - The contractor is still working in the Art & Music portable. Plumbing and electrical work will continue through Monday. The flooring work will be installed on Tuesday and should be completed Wednesday. The portable should be ready for move-in on Thursday, November 21st.
- 11.4.24 - Build back on both classrooms began last week
- 10.31.24 - Aristoi's COO met with the contractor and was informed that the materials required for the build back will be delivered Friday mid day. The contractor will be on campus Saturday morning to begin work with an estimated completion date of two weeks.
- Build back scheduled to begin October 31st. Anticipated completion is two weeks.
Front Building
- 11.15.24 - The contractor will install the remaining cabinets and countertops in the four classrooms in building one. The current plan is to have these installed late next week or early the following week so they are in place December 2nd.
Kinder and Fourth Grade Portables
- 11.15.24 - The remediation in the portables continues and we anticipate this work to be completed on Monday, November 18th. Once completed, air scrubbing will take 48 hours and we will then retest for clearance.
- Aristoi is working with vendors on a timeframe to restore and rebuild these portables.
Janitorial Services
- A new janitorial service began on October 24th for Katy campuses.
Campus Testing
- 11.4.24 - The Operations team will resume the testing of classrooms that have not yet been tested, weather permitting.
HVAC Units
- 11.4.24 - The four Bard units were successfully installed last week.
- 10.29.24 - Four new Bard units will be installed October 29th-October 31st. Two will be installed in D building and two in E building.
E Building
-
11.19.24 - No elevated levels of mold were identified as being present in the air samples collected in the E46 Classroom.
-
11.13.24 - No elevated levels of mold were identified as being present in the air samples collected in the E58 Classroom.
C Building
- 11.14.24 - The permit has been received from the City of Katy for the C building to continue remediation and build back.
- 11.4.24 - Currently waiting on permit from City of Katy. Once permit is received repairs to the east wall from south end to north end will be repaired.
- C1 and C18 subfloor moisture to be addressed.
- C2 and C15 remediation will continue.
B Building
- 11.11.24 -Remediation in the Science Lab (Building B) is complete. It was retested and cleared to reopen as of November 11, 2024.
- 11.4.24 - Remediation was completed today. Testing will take place on Wednesday, November 6.
- The builiding was shut down for remediation, which started October 29th, and is anticipated to be completed by Sunday, November 3rd. (No permit required per the City of Katy)
Drainage Plan
- Aristoi is working with a civil engineer on a plan to improve the drainage across the campus.
Janitorial Services
- A new janitorial service began on October 24th for Katy campuses.
This site provides information using PDF, visit this link to download the Adobe Acrobat Reader DC software.